Gravel Extras |
AUGUST 2000
Every railway requires a supply of ballast and fill for
its physical plant. Back in the 1940s and 1950s, the CNR maintained several sites which
supplied the needs of its various divisions. One of these supply pits was situated at
Colwell, just west of the division point of Allandale. We will take a close look at the
operations at this pit with an eye to replicating them on our miniature representations of
the CNR, CPR or other roads.
The CNR owned Colwell Pit, which was for company use only. In the 1940s
and 1950s, the pit was accessed from the Meaford Subdivision (see Steam
at Allandale, pages 80 and 113). Prior to that, it had been accessed from the Penetang
Subdivision, and in the late 1950s, it returned to the Penetang Subdivision as the Meaford
Subdivision pit had only poor quality material remaining. A temporary operator/timekeeper
was put on duty at Colwell station, located at the junction of the Meaford and Penetang
Subdivisions, for copying train orders when gravel trains were running in spring and
summer.
A rail-mounted Marion steam shovel with bucket worked in the pit (with
operator and assistant) loading ballast cars. As the shovel was self-propelled, the
operator could move cars around with it. Side or bottom dump gondola cars were moved to
the shovel by the crew as they were loaded, 25 to 30 at a time. The Association of
American Railroads (AAR) classification for these cars was MW. Characteristically, these
"MW" ballast cars were crowned "mug wumps" or "mud wagons"
by CNR men (see To Stratford Under Steam, pages 110 and 133,
for good pictures of them; not to be confused with cinder cars, which were cut-down
36-foot outside-braced boxcars). When ballast was too far away for the crane, the crew
moved the tracks closer, which was a simple operation. The shovel operator would move the
track (in about 10-foot sections) ahead of him. The pit crew carried sections of track.
Tracks would be moved by a bulldozer toward the new loading area after the gravel train
left (tracks were moved with each train load). The bulldozer and crane worked together. In
diesel times, when the steam crane was no longer available, crews spotted cars for a
diesel clam.
During the Second World War, the Colwell pit was very busy. Ballast
trains out of Colwell after the War ran one or two per day after the ground had dried up,
usually with Mikados. Operating crews were assigned to the pit for typically 4-6 weeks or
a couple of months, depending on roadbed work required on the division. At one time, the
pit worked six days per week for six months at a time. Colwell Pit was a very busy place
in summer months. As many as two trains of ballast (gravel) were loaded and shipped to
destinations on the Allandale Division daily. Two crews (one spotting, one loading) were
ordered between 4 and 5 a.m. The spotting crew headed out first thing in the morning with
a string of empties. After running around the empties at Colwell, cuts of ballast cars
were set up and loaded at the pit. Water for the engines was siphoned out of a creek south
of Colwell. The engine crew waited for loading, then headed back to Allandale with the
loads in the afternoon.
The work train was then ordered to take ballast out (and bring empties
back) wherever the work was being done. This involved a crew change. Other crews unloaded
the cars. Aprons between the cars allowed the entire length of train to be unloaded with a
winch. Gravel/ballast from the pit went everywhere in the vicinity (Bala, Toronto,
Newmarket, Milton, Orillia, Midland, Gravenhurst, etc.), but most went north. Material was
used for ballast or berms on sidings. A Jordan spreader was used to spread down banks.
Stone came from the Uhtoff Pit, just north of Orillia on the Midland Subdivision. There
was also a gravel pit near Sudbury (Cavell) which shipped to the west (the only other
place in the vicinity with a big operation). Wherever work was being done, the railway
would haul material from the nearest source of supply.
The operation at the pit dried up (wells had been drained by going too
deep) by about 1964, at the conclusion of work on the new MacMillan Yard (on the north
outskirts of Toronto). This sunset for the Colwell Pit represented the longest stretch of
work, six months from spring to freeze-up, at which time two trains of 70 to 80 cars ran
each day.
On numerous occasions, fellow modellers have asked me what we can use
to represent the mug wumps, as any modeller of the transition era (or any era, for that
matter) could use a string of gravel cars. Sadly, there is nothing readily available.
Years ago, Ulrich made a nice metal model of these cars in HO scale, but it has been
discontinued. Recently, both Red Caboose and Proto1000 have introduced general purpose
gondola cars in HO scale. While not overly similar to CNR cars, I don't believe a stand-in
train of these units would be a bad idea. I for one am not about to wait around for a
model of a relatively obscure prototype car to become available. If a reader of this
column is able to do a reasonable kitbashing job on one of these (or other) available
models, please e-mail me (ian@canadianbranchline.com)
the details and we'll feature the effort in a future column.
Ian Wilson
August 1, 2000
[HOME]
[ Topics ] [ Books ] [ Weblog ] [ Contact Us ] [ About Us ]